Agenda Item Title:  Slater/Vargas New Campus Project Modular Two-Story Building Change Order No. 1–Enviroplex, Inc.

Estimated Time: 

Person Responsible:  Ron Wheelehan, Interim Chief Business Officer



Background: 

During the Slater New Campus Modular Buildings Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $617,407.50 was budgeted for this project.

 

Change Order No. 1 for $220,632 will reduce the remaining contingency amount to $396,775.50 with 40% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order No. 1 will not exceed $220,632.00. A summary of Change Order No. 1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order No. 1 for the Slater New Campus Modular Two-Story Building Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Slater Vargas Two-Story Classrooms Enviroplex Change Order No. 1Backup Material2/27/2019