Agenda Item Title: Slater/Vargas New Campus Project Modular Buildings Change Order No. 2 Enviroplex, Inc.
Estimated Time:
Person Responsible: Ron Wheelehan, Interim Chief Business Officer
Background:
During the Slater New Campus Modular Buildings Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $279,096 was budgeted for this project.
Change Order #1 for $42,970 was approved on January 10, 2019.
Change Order #2 for $101,955 will reduce the remaining contingency amount to $134,171.78 with 55% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order No. 2 will not exceed $101,955.00. A summary of Change Order #2 is attached.
Recommended Action: That the Board of Trustees approve Change Order No. 2 for the Slater New Campus Modular Buildings Project.
|