During the Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $370,200 was budgeted for this project.

 

Change Order #1 for $246,208 was approved on February 1, 2018.
Change Order #2 for $71,020 was approved on May 3, 2018.
Change Order #3 for $15,573 was approved on September 6, 2018.

 

Change Order #4 for $(50,282.41) will increase the remaining contingency amount to $87,681.41 with 100% of the project complete.

 



Fiscal Implication:
The contingency monies required for Change Order #4 will not exceed $(50,282.41). A summary of Change Order #4 is attached.

Recommended Action: 

That the Board of Trustees approve Change Order #4 for the Stevenson Elementary School Project, Phase 2, Increment 1 Sitework Project.