Background:
During the Monta Loma Elementary School Phase 3 Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $354,408 was budgeted for this project.
Change Order #1 for $280,876 was approved on October 18, 2018.
Deductive Change Order #2 for ($15,569) will reduce the remaining contingency amount to $0 with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #2 will not exceed ($15,569). A summary of Change Order #2 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #2 for the Monta Loma Elementary School Phase 3 Project.