Mountain View Whisman School District

Agenda Item for Board Meeting of 1/24/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Benjamin Bubb Elementary School, Frank L. Huff Elementary School and Edith Landels Elementary School Multi-Use Rooms and Modernization Projects Phase 2 Change Order No. 2 Rodan Builders

Estimated Time: 

Person Responsible:  Robert Clark, Ed.D., Chief Business Officer



Background: 

During the Benjamin Bubb Elementary School, Frank L. Huff Elementary School and Edith Landels Elementary School Multi-Use Rooms and Modernization Projects Phase 2, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $1,801,977 was budgeted for this project.

 

Change Order #1 for $554,018 was approved on October 18, 2018.

 

Change Order #2 for $566,097 will reduce the remaining contingency amount to $681,862 with 99% of the project complete.

Fiscal Implication:

The contingency monies required for Change Order #2 will not exceed $556,097. A summary of Change Order #2 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #2 for the Benjamin Bubb Elementary School, Frank L. Huff Elementary School and Edith Landels Elementary School Multi-Use Rooms and Modernization Projects Phase 2.