Agenda Item Title:  Stevenson Elementary School Temporary Portable Disconnect Change Order No. 1– Galeb Paving, Inc.

Estimated Time: 

Person Responsible:  Robert Clark, Ed.D., Chief Business Officer



Background: 

During the Stevenson Elementary School Temporary Portable Disconnect Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $28,680 was budgeted for this project.

 

Change Order #1 for $7,804 will reduce the remaining contingency amount to $20,876 with 100% of the project complete.

 



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $7,804.00. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Stevenson Elementary School Temporary Portable Disconnect Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Stevenson Temporary Portable Disconnect - Galeb Change Order 1Backup Material12/18/2018