Item Coversheet

Mountain View Whisman School District

Agenda Item for Board Meeting of 1/10/2019



Agenda Category:  CONSENT AGENDA

Agenda Item Title:  Castro Elementary School Construction Project Phase 4 (Mistral Elementary School) - Change Order #1 - Enviroplex

Estimated Time: 

Person Responsible:  Robert Clark, Ed.D., Chief Business Officer



Background: 

During the Mariano Castro/Gabriela Mistral Elementary School Phase 4, Increment 2 Modular Classroom Building Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.

 

The total construction contingency of $140,437.85 was budgeted for this project.

 

Change Order #1 for $22,173 will reduce the remaining contingency amount to $118,264.85 with 100% of the project complete.



Fiscal Implication:

The contingency monies required for Change Order #1 will not exceed $22,173. A summary of Change Order #1 is attached.



Recommended Action: 

That the Board of Trustees approve Change Order #1 for the Mariano Castro/Gabriela Mistral Elementary School Phase 4, Increment 2 Modular Classroom Building Project.

ATTACHMENTS:
DescriptionTypeUpload Date
Castro Mistral Change Order 1 - EnviroplexBackup Material12/18/2018