Mountain View Whisman School District
Agenda Item for Board Meeting of 1/10/2019
Agenda Category: CONSENT AGENDA
Agenda Item Title: Castro Elementary School Construction Project Phase 4 (Mistral Elementary School) - Change Order #1 - Enviroplex
Estimated Time:
Person Responsible: Robert Clark, Ed.D., Chief Business Officer
Background:
During the Mariano Castro/Gabriela Mistral Elementary School Phase 4, Increment 2 Modular Classroom Building Project, unforeseen conditions, design changes, and owner requests have occurred, resulting in additions/changes in scope to the original project. These additions/changes require contingency money to be used.
The total construction contingency of $140,437.85 was budgeted for this project.
Change Order #1 for $22,173 will reduce the remaining contingency amount to $118,264.85 with 100% of the project complete.
Fiscal Implication:
The contingency monies required for Change Order #1 will not exceed $22,173. A summary of Change Order #1 is attached.
Recommended Action:
That the Board of Trustees approve Change Order #1 for the Mariano Castro/Gabriela Mistral Elementary School Phase 4, Increment 2 Modular Classroom Building Project.
|